D Line construction update

Construction begins at four new intersections in the next month

Emerson/Fremont & 26th

•     Construction began the week of Aug. 16. 

•     The intersection will be fully closed for 1 month with 2-3 months of lane restrictions following closure. 

•     Construction will include partial street reconstruction, street pavement, new station platforms, sidewalk, driveway apron, pedestrian ramps, signals, and utility work.

 Fremont & 42nd

•     Construction will begin the week of Sept. 6. 

•     The intersection will be fully closed for one month, with 3-4 months of lane restrictions following closure. 

•     Construction will include partial street reconstruction, new station platforms, sidewalk, driveway apron, pedestrian ramps, signals, and utility work. 

Construction continues at these intersections:  

Fremont & Dowling

•     Construction includes street pavement, new station platforms, sidewalk, pedestrian ramps, signals and utility work. 

•     Intersection partially closed the week of June 21 with lane restrictions in place for up to four months. 

•     Crews are completing work on the curb and gutter and began bus pad paving. Crews will continue the bus pad paving and begin electrical work 

Emerson/Fremont & Broadway

•     Construction includes station platforms, new pedestrian ramps, new signals and sidewalks, street pavement, and utility work. 

•     Intersection partially closed the week of June 14 with lane restrictions in place for up to four months. 

•     Crews continued work on the concrete station areas. This work will continue into next week. 

Emerson & Plymouth

•     Construction includes street pavement, new station platforms, sidewalk, pedestrian ramps, signals, and utility work. 

•     Intersection partially closed the week of June 12 with lane restrictions in place for up to three months. 

•     Crews continued work on landscaping around the shelter.  

Major construction has been completed at Fremont & 35th Ave. No traffic restrictions in place. Emerson/Fremont & Lowry: No traffic restrictions in place.

Up-to-date information can be found at metrotransit.org/alerts. Subscribe to Rider Alerts for up-to-date information. Experiencing construction issues? Please connect with our construction hotline at 612-568-1038. For more project information, visit metrotransit.org/d-line-project.