Fremont and 42nd
• Construction includes partial street reconstruction, new station platforms, sidewalk, driveway apron, pedestrian ramps, signals and utility work.
• Intersection fully closed Sept. 6, with a full closure in place for one month and 3-4 months of lane restrictions following closure.
• Crews began work on curb and gutter pouring and will begin electrical work and begin work on concrete station areas.
Fremont and Dowling
• Construction includes street pavement, new station platforms, sidewalk, pedestrian ramps, signals and utility work.
• Intersection partially closed with lane restrictions in place for up to four months.
Emerson/Fremont and 26th
• Construction includes partial street reconstruction, street pavement, new station platforms, sidewalk, driveway apron, pedestrian ramps, signals, and utility work.
• Intersection fully closed the week of Aug. 16 and 2-3 months of lane restrictions following closure.
• Crews completed electrical work and begin work on concrete station areas
Major construction has been completed at the following stations:
Fremont & 35th Ave. No traffic restrictions in place.
Emerson/Fremont & Lowry: No traffic restrictions in place.
Emerson/Fremont & Broadway: No traffic restrictions in place.
Emerson/Fremont & Plymouth: No traffic restrictions in place.
Route 5 detours continue in Minneapolis
Fremont Ave. and 42nd Detour
Find up-to-date info at metrotransit.org/alerts. Experiencing construction issues? Connect with our construction hotline at 612-568-1038. For more project info visit metrotransit.org/d-line-project.